Posted by Capital Projects on June 5, 2017 in General Announcements

Please be advised that Capital Projects requires the shutdown of one lane and sidewalk of the entrance/exit on the immediate west side of Cheb building per the photo. This shut down is necessary to replace the roof deck membrane on the Cheb Building under warranty.  The shut down will be in place from Tuesday June 6, 2017 to approx. July 5, 2017 (one month).  Safety barricades and signage will be in place.  One lane and the sidewalk on the far west side of the driveway along CRC will remain open.

We thank you for your understanding and patience.  Any questions or concerns can be addressed to:

Peter Coutts P. Eng., GSC

AVP Capital Projects