Today@Dal
» Go to news mainSUB Renovation Site Preparation
Site preparations for the Student Union Building Renovation Project will start Friday, July 24, with installation of fencing and preliminary work for demolition and renovation. The fencing will remain for the duration of the project, which is expected to be completed in the Fall of 2016.
This project involves mainly interior work to the basement, first, second, and third floors of the SUB totaling approximately 23,000 sf of the existing 104,000 sf building, as well as a new 1,500 sf entrance canopy expansion fronting on University Avenue and a 5,500 sf atrium expansion along LeMarchant Street.
There will be minimal disruption to vehicle traffic. Vehicular entry and exit through both gates to be assisted via traffic control. Deliveries will be scheduled before 8:00am and after 4:00pm whenever possible. Also there will be a loss of a few metered parking spaces between the SUB and Risley Hall. Access to the parking spaces will resume following the completion of this project.
If you have any questions or concerns please contact Project Manager, Garry Martell at 902-494-6484.
Recent News
- In Memoriam ‑ Colin Spinney
- Document delivery during Canada Post strike
- New surplus items added in Halifax
- Dal Tigers birthday parties
- Celebrate culture, creativity, and sustainability at the IEW Fashion Show!
- Student Accessibility Closure Friday, November 22
- Job postings
- Where suppliers can meet Dal Procurement