- Truck traffic will continue down through farm road as indicated on plan submitted.
- Shoring will commence shortly and noise in the area is expected.
- The relocation of underground communications will be happening over the next couple of weeks. Further notice will be given at a later time. It should be noted that an outage will occur affecting IT and possible other departments.
- Hot work activities ongoing in the existing plant
- Major deliveries expected over next 2 weeks would include cable tray system
Recent News
- Look Who's Talking ‑ Robert Larsen
- Lifting our communities
- FAFU Students Celebrate Mid‑Autumn Festival in Cox Kitchen
- Growing with Confidence: Shirley Thorn’s Journey as a Master Gardener in Training
- Flu shot Clinic on campus
- Bringing Worlds Together
- Funding Announced for Organic Science Cluster 4: Advancing the Sustainability of Canadian Agriculture
- Annapolis Royal Historic Gardens Field Trip