News

» Go to news main

Campus Construction Update

Posted by Stephanie Rogers on May 26, 2017 in News

The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.


Week of May 29th

Piping installation to continue in Chute, Boulden, Ruminant Animal Centre, Langille buildings and start in Haley and Jenkins Hall Buildings. (chance of minor noise with this work)

Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley and Jenkins Hall Buildings.

Electrical work to begin in Haley building. (Chance of minor noise with this work, hammer drilling)


Week of June 5th

Piping installation to continue in Langille, Haley and Jenkins Hall Buildings. (chance of minor noise with this work)

Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley, and Jenkins Hall Buildings.

Electrical work to continue in Haley building. (Chance of minor noise with this work, hammer drilling)

Any questions or concerns please contact:

Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca